H.B. 7
1
NET METERING OF ELECTRICITY
2
2002 GENERAL SESSION
3
STATE OF UTAH
4
Sponsor: Gordon E. Snow
5
This act modifies provisions relating to public utilities by enacting provisions relating to net
6
metering. This act requires electrical corporations to make a net metering program
7
available to customers by which customers may establish an inverter controlled customer
8
generation system to produce electricity for their own use and to supply excess electricity to
9
the electrical corporation. The act requires the electrical corporation to offset charges for
10
electricity by the amount of electricity supplied by a customer from a customer generation
11
system and requires the electrical corporation to give the customer a credit for electricity
12
generated by the customer that exceeds the amount supplied by the electrical corporation.
13
The act requires the customer to meet certain safety and other requirements with respect to
14
a customer generation system. The act prohibits the electrical corporation from imposing
15
additional charges or fees to customers participating in a net metering program unless
16
authorized.
17
This act affects sections of Utah Code Annotated 1953 as follows:
18
ENACTS:
19
54-15-101, Utah Code Annotated 1953
20
54-15-102, Utah Code Annotated 1953
21
54-15-103, Utah Code Annotated 1953
22
54-15-104, Utah Code Annotated 1953
23
54-15-105, Utah Code Annotated 1953
24
54-15-106, Utah Code Annotated 1953
25
Be it enacted by the Legislature of the state of Utah:
26
Section 1.
Section
54-15-101
is enacted to read:
27
CHAPTER 15. NET METERING OF ELECTRICITY
28
54-15-101. Title.
29
This chapter is known as "Net Metering of Electricity."
30
Section 2.
Section
54-15-102
is enacted to read:
31
54-15-102. Definitions.
32
As used in this chapter:
33
(1) "Customer-generated electricity" means electricity that:
34
(a) is generated by a customer participating in a net metering program from a customer
35
generation system;
36
(b) exceeds the electricity the customer needs for the customer's own use; and
37
(c) is supplied to the electrical corporation administering the net metering program.
38
(2) "Customer generation system" means a fuel cell or renewable facility that:
39
(a) has a generating capacity of not more than 25 kilowatts;
40
(b) is located on the premises of the electrical corporation's customer;
41
(c) operates in parallel and is interconnected with the electrical corporation's transmission
42
and distribution facilities;
43
(d) is intended primarily to offset part or all of the customer's requirements for electricity;
44
and
45
(e) is controlled by an inverter.
46
(3) "Excess customer-generated electricity" means the amount of customer-generated
47
electricity during a billing period that exceeds the amount of electricity that an electrical
48
corporation supplies to the customer during that billing period.
49
(4) "Fuel cell" means a device in which the energy of a reaction between a fuel and an
50
oxidant is converted directly and continuously into electrical energy.
51
(5) "Governing authority" means:
52
(a) for a distribution electrical cooperative, its board of directors; and
53
(b) for each other electrical corporation, the commission.
54
(6) "Inverter" means a device that:
55
(a) converts direct current power into alternating current power that is compatible with
56
power generated by an electrical corporation; and
57
(b) has been designed, tested, and UL certified to UL1741 and IEEE929 standards.
58
(7) "Net electricity" means the difference between:
59
(a) the amount of electricity that an electrical corporation supplies to a customer
60
participating in a net metering program; and
61
(b) the amount of customer-generated electricity.
62
(8) "Net metering" means measuring for the applicable billing period the difference
63
between:
64
(a) the amount of electricity that an electrical corporation supplies to a customer
65
participating in a net metering program; and
66
(b) the amount of customer-generated electricity.
67
(9) "Net metering program" means a program administered by a electrical corporation
68
whereby a customer with a customer generation system may:
69
(a) generate electricity primarily for the customer's own use;
70
(b) supply customer-generated electricity to the electrical corporation; and
71
(c) if net metering results in excess customer-generated electricity during a billing period,
72
receive a credit against the cost of electricity supplied by the electrical corporation to the customer
73
within the same calendar year.
74
(10) "Renewable facility" means a facility that uses energy derived from the sun, wind, or
75
water to generate electricity.
76
Section 3.
Section
54-15-103
is enacted to read:
77
54-15-103. Net metering program.
78
(1) Each electrical corporation shall:
79
(a) except as provided in Subsection (2), make a net metering program available to the
80
electrical corporation's customers; and
81
(b) allow customer generation systems to be interconnected to the electrical corporation's
82
facilities using, except as provided in Subsection (3), a standard kilowatt-hour meter capable of
83
net metering.
84
(2) An electrical corporation may discontinue making a net metering program available
85
to customers not already participating in the program as long as:
86
(a) the cumulative generating capacity of customer generation systems in the program
87
equals at least .1% of the electrical corporation's peak demand during 2001; and
88
(b) at least half of the electricity representing the .1% figure in Subsection (2)(a) is
89
generated by renewable facilities.
90
(3) (a) Notwithstanding Subsection (1)(b), an electrical corporation may require a customer
91
participating in the electrical corporation's net metering program to use metering equipment other
92
than a standard kilowatt-hour meter if the commission, after appropriate notice and opportunity
93
for comment:
94
(i) determines that the use of other metering equipment is necessary and appropriate to
95
monitor the flow of electricity from and to the electrical corporation; and
96
(ii) approves the requirement for other metering equipment, after considering the benefits
97
and costs associated with the other metering equipment.
98
(b) If the commission approves the requirement for other metering equipment under
99
Subsection (3)(a), the governing authority shall determine how the cost of purchasing and
100
installing the other metering equipment is to be allocated between the electrical corporation and
101
the customer.
102
(4) An electrical corporation may require a customer to enter into an interconnection
103
agreement before connecting the customer generation system to the electrical corporation's
104
facilities.
105
Section 4.
Section
54-15-104
is enacted to read:
106
54-15-104. Charges or credits for net electricity.
107
(1) Each electrical corporation with a customer participating in a net metering program
108
shall measure net electricity during each billing period, in accordance with normal metering
109
practices.
110
(2) If net metering does not result in excess customer-generated electricity during the
111
billing period, the electrical corporation shall bill the customer for the net electricity, in accordance
112
with normal billing practices.
113
(3) If net metering results in excess customer-generated electricity during the billing
114
period:
115
(a) (i) the electrical corporation shall credit the customer for the excess customer-generated
116
electricity at a value that is at least avoided cost;
117
(ii) the customer may use the credit under Subsection (3)(a)(i) to offset purchases of
118
electricity from the electrical corporation during future billing periods during the same calendar
119
year; and
120
(iii) all credits that the customer does not use during the calendar year expire at the end
121
of the calendar year; and
122
(b) the electrical corporation may bill the customer for customer charges that otherwise
123
would have accrued during that billing period in the absence of excess customer-generated
124
electricity.
125
Section 5.
Section
54-15-105
is enacted to read:
126
54-15-105. No additional fee or charge without commission approval -- Exception.
127
(1) An electrical corporation administering a net metering program may not charge a
128
customer participating in the program an additional standby, capacity, interconnection, or other fee
129
or charge unless the governing authority, after appropriate notice and opportunity for comment:
130
(a) determines that:
131
(i) the electrical corporation will incur direct costs from the interconnection or from
132
administering the net metering program that exceed benefits, as determined by the governing
133
authority, resulting from the program; and
134
(ii) public policy is best served by imposing the fee or charge on the customer participating
135
in the net metering program rather than by allocating the fee or charge among the electrical
136
corporation's entire customer base; and
137
(b) after making its determination under Subsection (1)(a), authorizes the additional fee
138
or charge.
139
(2) If a cost of a net metering program is allocated among the electrical corporation's entire
140
customer base, Subsection (1) may not be construed to prohibit an electrical corporation from
141
charging a customer participating in the net metering program for that cost to the same extent that
142
the electrical corporation charges a customer not participating in the program for that cost.
143
Section 6.
Section
54-15-106
is enacted to read:
144
54-15-106. Customer to provide equipment necessary to meet applicable code
145
requirements -- Allow for testing and inspection -- Commission may adopt additional
146
requirements.
147
(1) Each customer participating in a net metering program shall provide at the customer's
148
expense all equipment necessary to meet applicable local and national standards regarding
149
electrical and fire safety, power quality, and interconnection requirements established by the
150
National Electrical Code, the National Electrical Safety Code, the Institute of Electrical and
151
Electronics Engineers, and Underwriters Laboratories.
152
(2) After appropriate notice and opportunity for comment, the commission may by
153
regulation adopt additional safety, power quality, and interconnection requirements for customer
154
generation systems that the commission considers to be necessary to protect public safety and
155
system reliability.
156
(3) (a) If a customer participating in a net metering program complies with requirements
157
referred to under Subsection (1) and additional requirements established under Subsection (2), an
158
electrical corporation may not require that customer to:
159
(i) perform or pay for additional tests; or
160
(ii) purchase additional liability insurance.
161
(b) An electrical corporation may not be held directly or indirectly liable for permitting or
162
continuing to permit an interconnection of a customer generation system to the electrical
163
corporation's system or for an act or omission of a customer participating in a net metering
164
program for loss, injury, or death to a third party.
165
(4) An electrical corporation may test and inspect an interconnection at times that the
166
electrical corporation considers necessary to ensure the safety of electrical workers and to preserve
167
the integrity of the electric power grid.
Legislative Review Note
as of 9-12-01 1:58 PM
A limited legal review of this legislation raises no obvious constitutional or statutory concerns.
Office of Legislative Research and General Counsel
Committee Note
The Public Utilities and Technology Interim Committee recommended this bill.
[Bill Documents][Bills Directory]